We Make It Happen!










        
      Project Photos

     


        Contact: Blue Dog Construction, 1333 Carrison St., Berkeley, CA. 94702   Tel. 510-260-6058   email: ag@bluedogrenovation.com

           







      
     



        
      ROSE STREET, BERKELEY

    Basement Addition under existing Deck and Sunroom

    This project was started in October 2007 with some minor work being done to the first floor level which was basically street level. The new owner intended however to expand the basement into an additional family room as that room was located at the lower 'garden level' and would provide an ideal recreation place.

    The exisiting deck had at some stage had a sunroom built onto it. It wasn't possible to destroy this structure because it had been grandfathered in without permits some time ago, but an alteration could mean losing the opportunity of having a room up there at all. So when the basement extension was proposed, it was going to mean supporting the sunroom on a temporary structure whilst the new concrete foundations and slab below were poured.

    The deck was dismantled and the footings and foundations formed and poured. The extremely wet weather meant we had to tarp the entire job site, but that didn't prevent the trenches from being filled continuosly with water which we had to combat using an array of pumps and drains. The job site soon turned into a muddy nightmare of clay and dirt which covered everything, but it didn't stop us getting the rebar signed off after scrubbing it and the foudations pooured on the only sunny day in January.

    Once the foundations had been poured, we started framing the outside walls. The existing beam and supporting walls of the house were carried on temporary 4X4 posts within the existing basement. The new outside wall of the addition incorporated three large openings including two 6' wide French doors. To achieve the necessary stability, we opted to put in a single 26' long 91/2" deep PSL beam across the entire front. Once that was up and the framing was finished including the hold-downs for the shear walls, we sheathed much of the exterior using 1/2" structural OSB and rebuilt the deck using 4X6 joists. These carried 3/4" marine ply boards.

    The next step was pouring the slab which was completed just a couple of weeks later. This project is still in the works but is running on schedule and so far within the budget!